Restoration of a tennis court
Type of project
Restoration
Track Type
Clay court
Location
La Selva
Antiquity
about 18 years
Description
The back walls of a tennis court are not level with the baseline.
Features
The area lacked drainage, was very hard, and was uneven compared to the rest of the track.
The project consisted of
- Work on the affected area, starting from the baseline and moving outward about 3 meters outward and 1.5 to 2 meters inward
- Removal of the baseline and the top layer of clay
- Plow the surface until the entire area is thoroughly loosened
- Layered compaction of the area
- Installation of the new bottom lines
- Applying a layer of newly added compacted soil to the entire track