Restoration of a tennis court

9

Type of project

Restoration

9

Track Type

Clay court

9

Location

La Selva

9

Antiquity

about 18 years

Description

The back walls of a tennis court are not level with the baseline.

Features

The area lacked drainage, was very hard, and was uneven compared to the rest of the track.

The project consisted of

  • Work on the affected area, starting from the baseline and moving outward about 3 meters outward and 1.5 to 2 meters inward

  • Removal of the baseline and the top layer of clay

  • Plow the surface until the entire area is thoroughly loosened

  • Layered compaction of the area

  • Installation of the new bottom lines

  • Applying a layer of newly added compacted soil to the entire track